Visitor Center Update
COMPLETE
- Concrete slab is set 
- Slab edges cleaned and cleared for damp proofing 
- Concrete weir wall set at west end of bridge 
NEXT UP
- Steel delivery 
- Electric hook-up 
- Underground sanitary line from VC to septic tanks 
- Clearing and excavation for bridge abutments 
- Amphitheater foundation started 
- Stone at walking trail 
 
          
        
      